Selected work
From the tender table to the first shift.
Delivered live or completed work
Proposal tender or bid work
Design operating model or study
Al Jaber Group · Abu DhabiDelivered
Fleet transformation across three business units
- Challenge
- Managed transportation, limousine and valet units running on separate habits, with idle fleet and rising costs.
- Approach
- Centralised fleet control, preventive maintenance, SOPs and KPI reviews; disciplined purchasing and disposal across AED 16M+ of annual procurement.
- Outcome
- Utilization from 78% to 94%, operating costs down 18%, fleet off road under 1% and the valet unit grown by 164%.
Corporate headquarters tower · Riyadh · 2026Delivered
From contract award to live valet and stacking operation
- Challenge
- Five basements and 403 bays serving a headquarters and an academy, with peak demand well above fixed capacity.
- Approach
- Right sized team, a strict stacking order by level, colour coded windshield badges by floor and a separate visitor flow.
- Built
- Bilingual operating procedures (11 workflows, KPIs, four level escalation) and a web app that lets employees release a blocked car by typing plate digits only: no sign in, no install, with audit log and admin KPIs.
Office campus, 1,465 spaces · Riyadh · 2026Proposal
Closing a 285 space gap without charging tenants for what they are owed
- Challenge
- Lease entitlements at full occupancy required 1,750 spaces against 1,465 available across puzzle and conventional parking.
- Approach
- Entitlement kept free; system assigned virtual zones enforced by LPR; data triggered valet stacking for the overflow; paid options only above entitlement. Seven services phased with occupancy, integrated with the existing PMS.
- Decision
- Dropped an already approved model that charged tenants per stacked space, and replaced it with a landlord funded, pay per use capacity service.
Mixed use district, 1,093 spaces · RiyadhProposal
Phased parking O&M tender and a renewal model that reproduces last year
- Approach
- Paid parking first, access control and subscriptions second, physical upgrades only after licensing and six months of real operating data.
- Model
- A forecasting model built on about 118,000 annual transactions, with validation rates by outlet, a minimum annual guarantee wired into the P&L and good, okay and walk away scenarios.
- Test
- The model had to reproduce the prior year's actual P&L before anyone trusted its forecast.
Integrated healthcare mobility for 24 hospitals and 78 clinics
- Scope
- A nationwide transport model for Abu Dhabi Healthcare Services: 540+ vehicles and 600 drivers.
- Approach
- Fleet sizing, routing and scheduling, a five year asset and financial plan, and hybrid and EV transition options.
Saudi Arabia & UAE · 2022 to 2023Delivered
Major event mobility
- Events
- Formula One Abu Dhabi: traffic and valet with 130+ personnel. World Combat Games and Saudi Games 2023 in Riyadh: transport planning and execution.
- Work
- Route planning, fleet allocation, peak demand sizing, depot management and live monitoring against fixed event deadlines.
Stadium RFP · Saudi ArabiaDecision
Choosing not to bid
- Context
- After contributing to the market sounding, the final RFP excluded event days from scope, which removed the demand that made the operation viable.
- Decision
- We declined to bid and sent a regret letter that kept the relationship open. Bid selectively, then commit fully: a tender we cannot run well is not worth winning.